it takes 20 people 24 days to build a barn. in how many days will the barn be built if they had 32 people working

Respuesta :

bluevortexwitepower bluevortexwitepower
  • 02-02-2019

Answer:

15 days

Step-by-step explanation:

Number of ppl it takes to build a barn in 24 days=20

Time it will take 32 people to build the barn=24*20/32=15 days

Answer Link

Otras preguntas

A six−sided die, with sides numbered 1,2, 3,4,5, and 6, is tossed. What is the probability of tossing a number less than three?
How did the formation of alliances affect the outbreak of war?
a couple wants to install a square mirror that has an area of 500 square inches.to the nearest tenth of an inch,what length of wood trim is needed to go aroun
8. A pattern of being late for work or for appointments is usuallyA. a habit learned early, which is nearly impossible to break.B. directly related to one's per
All of the following are true about Latinos’ experiences in World War II EXCEPT (A) unlike African Americans, Latinos fought in integrated units (B) Latino you
What conditions must be met in order for a reaction to be considered exothermic?
what is this number in word form 3,152,308,726
what is 69/25 as a terminating decimal
What Was Jackson’s perspective on the McCulloch v. Maryland Supreme Court Case
How do I solve c/4d divided by 3/8d