Answer:
the predetermined overhead rate is $35.28
Explanation:
The computation of the predetermined overhead rate is given below:
The Predetermined overhead rate is
= Estimated overhead Ă· Capacity hours
= $2,836,512 Ă· 80,400 machine hours
= $35.28
hence, the predetermined overhead rate is $35.28