For a process, the average range for all samples was 5 and the process average was 25. If the sample size was 10, calculate UCL for the R-chart.

Respuesta :

fichoh
fichoh fichoh
  • 07-06-2021

Answer:

8.885

Step-by-step explanation:

Given that :

Sample size, n = 10

The average range, Rbar for all samples = 5

The upper control limit, UCL for the R-chart is :

UCL L= D4Rbar

From the control chart constant table, D4 = 1.777

Hence,

UCL = 1.777 * 5

UCL = 8.885

The UCL for the R-chart is 8.885

Answer Link

Otras preguntas

Which of the following is a characteristic of resilience? having more highly developed learned emotions than primary ones being more introverted than extroverte
which of the following describes temperature
Solve the equation; 2x-1=3
Each of 25 students in group A read for 45 minutes. Each of 21 students in group B read for 48 minutes. Which group read from more minutes explain
5 7/8 in to a improper fraction
What is the job of a storyteller in the giver
Who were the mercenaries that fought with the british army in the revolutionary war?
How many cotyledons would be found in a flowering plant with 9 petals on each flower and long leaves with parallel leaf veins?
Are earthquakes scattered all over the world or do they seem to occur near each other (in groups)?
Which pair of concepts is most likely to be symbolized by a hawk and a dove in a literary work? a benefactor and a grateful beneficiary a doting parent and a ch