Activity A B C D E F G H Time 5 3 7 6 7 3 10 8 a. Identify the critical path. b. How much time will be needed to complete this project

Respuesta :

aristeus aristeus
  • 06-07-2021

Answer:

Critical path = A-D-F-H

Duration = 22

Explanation:

Given:

Activity A B C D E F G H

Time 5 3 7 6 7 3 10 8

The objective is to identify the critical path and to find the time needed to complete this project

Solution:

The possible paths are as follows,

A-C-H = 5+7+8 =20

A-D-F-H = 5+6+3+8 =22

A-D-G = 5+6+10 = 21

B-E-G = 3+7+10 = 20

B-E-F-H = 3+7+3+8 = 21

a)

Critical is the path with the longest duration

Critical path =A-D-F-H

The duration is 22

b)

The duration to complete the project is as follows,

Duration = Length of critical path = 22

Answer Link

Otras preguntas

The measure of angle 7 = 100 what is the angle of 3
What does each letter stand for in Einstein’s equation, E=mc2? State in words what Einstein’s equation represents. Explain why Einstein’s equation is so importa
Summer says "Attends une minute! Maintenant je m'en souviens. That's the musée avec les oeufs extraordinaires." What are les oeufs extraordinaires? golden eggs
What products were being shipped out of Egypt? Gold, linen, papyrus.
0.9d-2.1f Helpp!!❗‼️
What is the name of all of the images shown?
1. If a cell has waste it needs to store, it will store it:​
What is the probability of randomly selecting an odd number from the numbers 1 - 15?
Please please help me please:(
1. Do you think it’s important to know what you’re eating, i.e. where it came from, how it was produced? Why or why not? 2. Do you read food labels and really k