In a project network, the critical path is the sequence of activities which has the:________.

Respuesta :

66hello60
66hello60 66hello60
  • 03-08-2022

Answer:

The correct answer is the longest time

Answer Link

Otras preguntas

1. The movements of energy and nutrients through living systems are different because (1 point) energy flows in one direction, and nutrients recycle. energy is
Which tool will help you replace overused words in a text? a. Dictionary b. Spell check c. Thesaurus d. Wikipedia
1. What are goals of science? Choose all that apply. (3 points) to investigate the natural world ) to establish unchanging facts to explain natural phenome
How would i respond to these? . ¿Quién habla contigo?. ¿Cuándo estudias con ella?. ¿Qué escuchas con ellos?. ¿Dónde practicas el español conmigo?. ¿Qué miras co
Which excerpt from the poem “Tattoo” by Gregg Shapiro is a symbol for the Holocaust experience? a. “blue as blood on his left forearm” b. “spilling his protecti
a container holds 100 teaspoons of water. what might the container look like? include dimensions
What is the correct way of asking someone how well they did in their exams? -How did your exams go?. -How do your exams went?. -How did your exams went?. Ple
Which step can be used to prove that triangle EFG is also a right triangle? Prove that the sum of a and c is greater than b. Prove that the sum of a and b is gr
Which of the following might be described as a recreational activity?
A force that acts on an object but does not touch it is a