Is typically not referred to as a buffer type in critical chain project management?

Respuesta :

dinosaurbarn
dinosaurbarn dinosaurbarn
  • 14-01-2018

The answer is Free Buffer. Project buffer, a not usual and the only one buffer to protect the project deadline;

Feeding buffer it is different types of buffers to protect parts of the critical chain. And resource buffer is a multiple artificial buffers that act as warning signals to assure that it is available of resources.

Answer Link

Otras preguntas

When something stands out from a background, is seen as important, or draws attention it is:?
Why did the anti federalists believe the constitution was a class based document?
How do you write 7,285,000.000 in scientific notation?
Ehrenreich provides fairly extensive commentary in footnotes. what is the effect of this strategy? in the footnotes, is her tone different from the one used in
At what point does the terminal side of the angle π in standard position intersect the unit circle?
1/3 if the guests choose beef 5/12 of the guests choose chicken and 23 of the guest choose vegetarian how many guests were at the wedding
Find the quotation 81 ÷ 10,000
What is the task of production and operations management?
Education, experiences, social and cultural expectations, and religious beliefs are called a listener's A. reference points. B. defense mechanisms.
PLS HELP!!!!!!!!!!!!!!! A man and woman have a son who is color blind, a recessive sex-linked trait carried on the X-chromosome, but neither parent is color bli